Banchory Sports Centre

Contracted by:
McLaughlin & Harvey
Who was the project for:
Aberdeenshire Council
What service were you asked to provide:
Structural steelwork, curved glulam rafters, metal decking, steel stairs.
Start date:
June 2018
Delivery:
11 Weeks
Project specifications:

This project involved approx. 320 tons of steelwork carried out in two phases. SCL utilised their own directly employed labour to erect the steel frame on site with the aid of MEWPS. This contract included the fitting of 9 timber glulam rafters and associated purlins and form the swimming pool roof.  

The glulams were sourced from Austria were installed by SCL at the same time as the steel frame.  Steel erection on site required considerable interaction with groundworks trades to ensure programme deadlines were met.

With the project complete we produced this incredible timelapse showing the progress of the Banchory Sports Centre.